Montagne d’Huilly
Municipalities: Allerey
Type of wind turbines: N131/3000
Total power of the farm: 15 MW
Number of wind turbines:
Commissioning date: Q4 2022
Auvergne-Rhône-Alpes

Bourgogne-Franche-Comté

-
Côte d’Or
Bretagne

-
Côtes-d'Armor
Coatjégu
Municipalities: Plédéliac, Plestan
Type of wind turbines: N117 R91
Total power of the farm: 7,5 MW
Number of wind turbines: 3
Commissioning date: April 2020 -
Finistère
Plomodiern
Municipality: Plomodiern
Type of wind turbines: N80/2500
Total power of the farm: 12,5 MW
Number of wind turbines: 5
Commissioning date: June 2009
Centre-Val de Loire

-
Cher
Bois Ballay
Municipality: Mareuil-sur-Arnon
Type of wind turbines: N100/2500
Total power of the farm: 12,5 MW
Number of wind turbines: 5
Commissioning date: September 2011La Chaussée de César Nord
Municipality: Civray
Type of wind turbines: N100/2500
Total power of the farm: 10 MW
Number of wind turbines: 4
Commissioning date: July 2013La Chaussée de César Sud
Municipality: Civray
Type of wind turbines: N100/2500
Total power of the farm: 10 MW
Number of wind turbines: 4
Commissioning date: August 2013Forges
Municipalities: Saint-Ambroix, Mareuil-sur-Arnon
Type of wind turbines: N100/2500
Total power of the farm: 12,5 MW
Number of wind turbines: 5
Commissioning date: September 2011Les Coudrays
Municipality: Sainte-Thorette
Type of wind turbines: N100/2500
Total power of the farm: 10 MW
Number of wind turbines: 4
Commissioning date: May 2011Les Croquettes
Municipality: Quincy
Type of wind turbines: N100/2500
Total power of the farm: 12,5 MW
Number of wind turbines: 5
Commissioning date: December 2011Les Mistandines
Municipality: Sainte-Thorette
Type of wind turbines: N100/2500
Total power of the farm: 10 MW
Number of wind turbines: 4
Commissioning date: March 2011Longchamp
Municipality: Nohant-en-Graçay
Type of wind turbines: N100/2500
Total power of the farm: 10 MW
Number of wind turbines: 4
Commissioning date: November 2011Saint-Ambroix
Municipality: Saint-Ambroix
Type of wind turbines: N131/3000
Total power of the farm: 12 MW
Number of wind turbines: 4
Commissioning date: April 2019 -
Eure-et-Loir
Bois Bigot
Municipality: Boisville-la-Saint-Père
Type of wind turbines: N90/2300
Total power of the farm: 9,2 MW
Number of wind turbines: 4
Commissioning date: February 2006Bois Clergeons
Municipalities: Poinville, Janville-en-Beauce
Type of wind turbines: N90/2300
Total power of the farm: 11,5 MW
Number of wind turbines: 5
Commissioning date: November 2005Bois de l'Arche
Municipality: Beauvilliers
Type of wind turbines: N90/2300
Total power of the farm: 11,5 MW
Number of wind turbines: 5
Commissioning date: March 2006La Butte Saint-Liphard
Municipalities: Oinville-Saint-Liphard, Janville-en-Beauce
Type of wind turbines: N90/2500
Total power of the farm: 10 MW
Number of wind turbines: 4
Commissioning date: May 2007Le Carreau
Municipality: Terminiers
Type of wind turbines: N90/2300
Total power of the farm: 9,2 MW
Number of wind turbines: 4
Commissioning date: June 2006Le Champ Besnard
Municipality: Santilly
Type of wind turbines: N90/2500
Total power of the farm: 10 MW
Number of wind turbines: 4
Commissioning date: July 2007Les Hauts de Melleray
Municipalities: Oinville-Saint-Liphard, Janville-en-Beauce
Type of wind turbines: N90/2500
Total power of the farm: 10 MW
Number of wind turbines: 4
Commissioning date: July 2007Les Trois Muids
Municipality: Terminiers
Type of wind turbines: N90/2300
Total power of the farm: 11,5 MW
Number of wind turbines: 5
Commissioning date: May 2006Voie Blériot Est
Municipalities: Poinville, Santilly
Type of wind turbines: N90/2300
Total power of the farm: 11,5 MW
Number of wind turbines: 5
Commissioning date: November 2005Voie Blériot Ouest
Municipalities: Poinville, Santilly
Type of wind turbines: N90/2300
Total power of the farm: 11,5 MW
Number of wind turbines: 5
Commissioning date: April 2006 -
Indre
Aubigeon
Municipalities: Diou, Sainte-Lizaigne
Type of wind turbines: N100 R100 2500
Total power of the farm: 12,5 MW
Number of wind turbines: 5
Commissioning date: July 2015Barbes d'Or
Municipality: Migny
Type of wind turbines: N90/2500
Total power of the farm: 12,5 MW
Number of wind turbines: 5
Commissioning date: April 2009Les Joyeuses
Municipality: Saint-Georges-sur-Arnon
Type of wind turbines: N90/2500
Total power of the farm: 10 MW
Number of wind turbines: 4
Commissioning date: September 2009Les Pierrots
Municipalities: Saint-Georges-sur-Arnon, Migny
Type of wind turbines: N117/2400 TS98
Total power of the farm: 26,4 MW
Number of wind turbines: 11
Commissioning date: July 2021Les Tilleuls
Municipality: Saint-Georges-sur-Arnon
Type of wind turbines: N90/2500
Total power of the farm: 12,5 MW
Number of wind turbines: 5
Commissioning date: June 2009Les Vignes
Municipality: Saint-Georges-sur-Arnon
Type of wind turbines: N90/2500
Total power of the farm: 12,5 MW
Number of wind turbines: 5
Commissioning date: June 2009Paudy
Municipality: Paudy
Type of wind turbines: N117/3000
Total power of the farm: 15 MW
Number of wind turbines: 5
Commissioning date: August 2019Pelures Blanches
Municipalities: Diou, Sainte-Lizaigne, Paudy
Type of wind turbines: N100/2500
Total power of the farm: 12,5 MW
Number of wind turbines: 5
Commissioning date: June 2015 -
Loiret
Bois Louis
Municipality: Tournoisis
Type of wind turbines: N90/2300
Total power of the farm: 11,5 MW
Number of wind turbines: 5
Commissioning date: April 2006Le Sainbois
Municipality: Tournoisis
Type of wind turbines: N90/2300
Total power of the farm: 11,5 MW
Number of wind turbines: 5
Commissioning date: April 2006Les Bornes de Cerqueux
Municipality: Épieds-en-Beauce
Type of wind turbines: N90/2500
Total power of the farm: 12,5 MW
Number of wind turbines: 5
Commissioning date: August 2007 -
Loir-et-Cher
Les Mardeaux
Municipalities: Ouzouer-le-Doyen, Moisy
Type of wind turbines: N90/2300
Total power of the farm: 11,5 MW
Number of wind turbines: 5
Commissioning date: Oktober 2006Les Pénages
Municipalities: Moisy, Beauce-la-Romaine
Type of wind turbines: N90/2300
Total power of the farm: 11,5 MW
Number of wind turbines: 5
Commissioning date: May 2006Viertiville
Municipality: Binas
Type of wind turbines: N90/2300
Total power of the farm: 11,5 MW
Number of wind turbines: 5
Commissioning date: July 2006
Grand Est

-
Ardennes
Vents de Thiérache 1
Municipalities: Auvillers-les-Forges, Champlin, Antheny
Type of wind turbines: N100/2500
Total power of the farm: 15 MW
Number of wind turbines: 6
Commissioning date: September 2013Vents de Thiérache 2
Municipalities: Champlin, Antheny
Type of wind turbines: N100/2500
Total power of the farm: 12,5 MW
Number of wind turbines: 5
Commissioning date: July 2013 -
Aube
SRN
Municipalities: Mesgrigny, Vallant-Saint-Georges, Châtres, Orvilliers-Saint-Julien
Type of wind turbines: N100/2500
Total power of the farm: 75 MW
Number of wind turbines: 30
Commissioning date: April 2015 -
Bas-Rhin
Dehlingen
Municipality: Dehlingen
Type of wind turbines: N90/2500
Total power of the farm: 12,5 MW
Number of wind turbines: 5
Commissioning date: July 2013
-
Meurthe-et-Moselle
Fillières
Municipality: Fillères
Type of wind turbines: N90/2500
Total power of the farm: 10 MW
Number of wind turbines: 4
Commissioning date: July 2012
-
Moselle
Fresnes-en-Saulnois
Municipality: Fresnes-en-Saulnois
Type of wind turbines: N90/2300
Total power of the farm: 11,5 MW
Number of wind turbines: 5
Commissioning date: July 2008Morlange
Municipalities: Brouck, Bionville-sur-Nied, Bannay
Type of wind turbines: N117/4500
Total power of the farm: 9,6 MW
Number of wind turbines: 4
Commissioning date: November 2016Zondrange
Municipalities: Fouligny, Bionville-sur-Nied, Marange-Zondrange
Type of wind turbines: N100/2500
Total power of the farm: 12,5 MW
Number of wind turbines: 5
Commissioning date: December 2016
Hauts de France

-
Aisne
Autremencourt (extension)
Municipalities: Autremencourt, Cuirieux
Type of wind turbines: N117/2400
Total power of the farm: 14,4 MW
Number of wind turbines: 6
Commissioning date: March 2019Epine Marie-Madeleine
Municipalities: Agnicourt-et-Séchelles, Chaourse, Montigny-le-Franc
Type of wind turbines: N117
Total power of the farm: 36 MW
Number of wind turbines: 12
Commissioning date: October 2018Epine Marie-Madeleine (extension)
Municipalities: Tavaux-et-Pontséricourt, Montigny-le-France, Agnicourt-et-Séchelles
Type of wind turbines: N131/3250
Total power of the farm: 22,8 MW
Number of wind turbines: 7
Commissioning date: Q3 2022Le Moulin à Vent
Municipalities:Coupru
Type of wind turbines: N117/2400
Total power of the farm: 12 MW
Number of wind turbines: 5
Commissioning date: Q4 2022 -
Oise
Breteuil-Esquennoy
Municipalities: Breteuil, Esquennoy
Type of wind turbines: N90/2500
Total power of the farm: 12,5 MW
Number of wind turbines: 5
Commissioning date: March 2019Breteuil-Paillart
Municipalities: Breteuil, Paillart
Type of wind turbines: N90/2300
Total power of the farm: 11,5 MW
Number of wind turbines: 5
Commissioning date: May 2007Hétomesnil
Municipality: Hétomesnil
Type of wind turbines: N90/2300
Total power of the farm: 11,5 MW
Number of wind turbines: 5
Commissioning date: August 2006Hétomesnil II
Municipality: Hétomesnil
Type of wind turbines: N100/2500
Total power of the farm: 12,5 MW
Number of wind turbines: 5
Commissioning date: July 2016Le Cornouiller
Municipalities: Thieux, Noyers-Saint-Martin
Type of wind turbines: N90/2300
Total power of the farm: 11,5 MW
Number of wind turbines: 5
Commissioning date: January 2007Les Hauts Bouleaux
Municipalities: Thieux
Type of wind turbines: N117 TS76/3000c
Total power of the farm: 18 MW
Number of wind turbines: 6
Commissioning date: April 2022Lihus
Municipality: Lihus
Type of wind turbines: N90/2300
Total power of the farm: 11,5 MW
Number of wind turbines: 5
Commissioning date: September 2006Lihus II
Municipality: Lihus
Type of wind turbines: N100/2500
Total power of the farm: 10 MW
Number of wind turbines: 4
Commissioning date: March 2016Noyers et Bucamps
Municipalities: Bucamps, Noyers-Saint-Martin
Type of wind turbines: N100/2500
Total power of the farm: 10 MW
Number of wind turbines: 4
Commissioning date: December 2018 -
Pas-de-Calais
Graincourt
Municipality: Graincourt-lès-Havrincourt
Type of wind turbines: N117/3000
Total power of the farm: 12 MW
Number of wind turbines: 4
Commissioning date: May 2019Le Chemin de Mory
Municipalities: Écoust-Saint-Mein, Mory
Type of wind turbines: N117 TS91; N131 TS120
Total power of the farm: 23,175 MW
Number of wind turbines: 6
Commissioning date: July 2020Mont d'Erny
Municipalities: Enquin-lez-Guinegatte, Delettes
Type of wind turbines: N100/2500
Total power of the farm: 12,5 MW
Number of wind turbines: 5
Commissioning date: June 2017 -
Somme
Eplessier
Municipality: Éplessier
Type of wind turbines: N100/2500
Total power of the farm: 32,5 MW
Number of wind turbines: 13
Commissioning date: January 2017Le Douiche
Municipalities: Fins, Sorel, Heudicourt
Type of wind turbines: N117/3000
Total power of the farm: 60 MW
Number of wind turbines: 20
Commissioning date: March 2019Martinpuich
Municipality: SMartinpuich, Le Sars
Type of wind turbines: N117/3675
Total power of the farm: 14,4 MW
Number of wind turbines: 4
Commissioning date: March 2022
Île-de-France

-
Essonne
Boissy-la-Rivière
Municipality: Boissy-la-Rivière
Type of wind turbines: N90/2500
Total power of the farm: 15 MW
Number of wind turbines: 6
Commissioning date: September 2017
Normandie

-
Calvados
Ondefontaine
Municipality: Les Monts d'Aunay
Type of wind turbines: N100/2500
Total power of the farm: 10 MW
Number of wind turbines: 4
Commissioning date: April 2016 -
Seine-Maritime
Mont des Mares / Mont Martin
Municipalities: Smermesnil, Saint-Pierre-des-Jonquières
Type of wind turbines: N117/3000
Total power of the farm: 15 MW
Number of wind turbines: 5
Commissioning date: October 2017Plaine de Beaunay
Municipality: Saint-Pierre-Bénouville
Type of wind turbines: N100/2500
Total power of the farm: 12,5 MW
Number of wind turbines: 5
Commissioning date: October 2017Val aux Moines
Municipalities: Vatierville, Fesques
Type of wind turbines: N100/2500
Total power of the farm: 15 MW
Number of wind turbines: 6
Commissioning date: September 2017
Nouvelle Aquitaine

-
Charente-Maritime
Grand Champ Pelé
Municipalities: Mazeray, Bignay
Type of wind turbines: N90/2500
Total power of the farm: 12,5 MW
Number of wind turbines: 5
Commissioning date: August 2012
Occitanie

Pays de la Loire

-
Loire-Atlantique
Campbon
Municipality: Campbon
Type of wind turbines: N90/2500
Total power of the farm: 12,5 MW
Number of wind turbines: 5
Commissioning date: June 2009Les Touches
Municipality: Les Touches
Type of wind turbines: N100/2500
Total power of the farm: 15 MW
Number of wind turbines: 6
Commissioning date: June 2015
-
Maine-et-Loire
Hyrôme
Municipality: Chemillé-en-Anjou
Type of wind turbines: N117 R93
Total power of the farm: 12 MW
Number of wind turbines: 5
Commissioning date: March 2020La Jacterie
Municipalities: Chemillé-en-Anjou, Trémentines
Type of wind turbines: N100/2500
Total power of the farm: 12,5 MW
Number of wind turbines: 5
Commissioning date: August 2016Le Fouy
Municipality: Chemillé-en-Anjou
Type of wind turbines: N90/2500
Total power of the farm: 10 MW
Number of wind turbines: 4
Commissioning date: December 2008Le Pâtis
Municipalities: Chemillé-en-Anjou, Beaupréau-en-Mauges
Type of wind turbines: N100/2500
Total power of the farm: 7,5 MW
Number of wind turbines: 3
Commissioning date: June 2013Les Crêtes
Municipalities: Coron, Chemillé-en-Anjou
Type of wind turbines: N90/2500
Total power of the farm: 10 MW
Number of wind turbines: 4
Commissioning date: December 2008Vihiersois
Municipalities: Saint-Paul-du-Bois, Lys-Haut-Layon
Type of wind turbines: N117/2400
Total power of the farm: 21,6 MW
Number of wind turbines: 9
Commissioning date: July 2019